SIKU BASIN ARMY FAMILY HOUSING
FT. WAINWRIGHT, ALASKA
The ambitious project schedule presented one challenge, as did the site itself, which
required complex site work, further complicated by the difficulty of permafrost
conditions and an abbreviated construction season due to the sub-arctic climate.
Additionally, this was the first Fort Wainwright housing project designed to
utilize Fairbanks municipal utilities, rather than Base utilities, which required
a high level of coordination with four different municipal utilities in both the
design and construction phases of the project.
Despite these challenges, each phase of the aggressive turnover schedule was
completed at least three months early and the project was approximately $400,000
under budget – even with the implementation of numerous improvements made during
construction for the benefit of the users and to reduce life-cycle maintenance
cost. As a result of the early completion, Fort Wainwright soldiers received
10,686 additional days of occupancy.
KEY PROJECT FEATURES
Design and construction of 126 Total Family Housing Units
Site Development for Utilities, Roads, Sidewalks
Play Areas
Construction Cost:
$72 million
Completion Date:
September 2008